September 2019 SAGE Maintenance Release

SPAERC & SERA

Updates to Post-Award Change (PAC)

In order to improve the data quality, reporting, and analytics around award data, the following changes have been made to the Post-Award Change in SPAERC and SERA:

  • Addition of Revised Start Date field, displayed for the PAC Requested Change type “Start Date Change”
  • Addition of Revised End Date field, displayed for PAC Requested Change types “Extension”, “Early Termination”, or “Relinquishment”
  • Addition of Temporary End Date field, displayed for PAC Requested Change type “Temporary Budget Extension” (formerly called “Advanced Extension”)
  • Addition of Modification Number field
  • Addition of Originating Sponsor Award Number field, which will pre-populate from the parent FA data, when present.

Updates to PAC Notification PDF

The above new PAC fields will also be displayed on the PDF attachment that is sent to campus when a PAC has been processed.

Updates to Pending Actions Report

The above new PAC fields are also included on the GCA Pending Actions Report

PAC Requested Change Type Updates

The following changes have been made to existing PAC types:

  • “Advanced Extension” is now relabeled as “Temporary Budget Extension”
  • “Significant Financial Interest” has been removed
  • “Create Program Income” has been removed
  • “Change of Award” has been removed
  • “Change in Authorized Action” has been removed

The removed PAC Requested Change types will continue to display on historical PACs.

Update to Cycle View of PAC Data

When in the SPAERC or SERA Cycle view, the PAC row will now display the new Revised Start Date, Revised End Date, and Temporary End Date fields when populated.

Intellectual Property Provisions validation message update

The validation message that appears when the Intellectual Property Provisions question is not answered will now match the current question label, for added clarity.

SPAERC only: Grant Runner Submit no longer displays timeout error

Upon submission of Grant Runner applications in SPAERC, the system was displaying time-out errors that were misleading and likely to cause unnecessary alarm or confusion. The error tracking has been updated to improve the quality of the messages received by OSP on submission.

SPAERC only: Activity Locations Page Expanded by Default

The eGC1 Activity Locations page in SPAERC will now display as expanded by default, for easier viewing of relevant data without additional clicks.

You can add holds to Applications, Funding Actions, or any type of Admin Action. You can also modify or remove existing holds whether added manually or automatically by the system.

There are two categories of hold reasons: Non-Compliance and Compliance.

Non-Compliance hold reasons are:

  • For Check
  • Other (Campus)
  • Other (Sponsor)
  • Pending Fully Executed Agreement
  • Pending Notice to Process/Activation Notice
  • PI Signature
  • Revised Budget

Compliance hold reasons are:

  • Administrative Support
  • Cost Share
  • Export Control
  • F&A
  • Federal Flow-Through
  • IACUC Approval
  • IRB Approval
  • SFI/FCOI
  • PHS Training

Automatic Holds

  • Applications: If there is an Export Control watcher on the approval flow, when the application reaches In OSP status, the system will automatically add an Export Control compliance hold. Manually added holds on Applications do not enforce any process rules.
  • Actions: The system will automatically place some compliance holds on Funding Actions and Post-Award Changes. See the section on Automatic Holds for further details.

Add a Hold

  1. On the left navigation menu, select Add/Modify Hold
  2. In the dialog window that opens, check one or more hold reason boxes. The dialog window is shown in the following image for a Funding Action.

add or modify holds

    1. Enter any optional OSP notes about the holds
    2. Click Save to complete the process.

Note: When you open the Add/Modify Hold dialog window after the first time, you will see an expandable bar below the list of holds titled “Previous OSP Note Hold Reason Comments.” Click on the bar to expand the section.  A table displays that shows the date entered, the comment, and who the comment was entered by. The same information also displays under the OSP Notes tab. Clicking the bar again will hide the table. This section is shown expanded in the above image.

A yellow “On Hold” banner will display at the top of the item’s details page. The following image shows the banner on a Funding Action.

on hold banner

Modify or Remove a Hold

  1.  Select Add/Modify Hold to open the dialog window
  2. Adjust the selected hold reasons
  3. Add an optional comment
  4. Click Save

If you clear all of the check boxes, the item will no longer be on hold and the banner and tasklist icons will no longer display.

You can change any Funding Action or Admin Action in Approved, Denied, Duplicate, or Returned by GCA status back to In OSP status. Use the In OSP link on the left navigation menu to start the process.

action left menu in O S P choice

A pop-up window will appear that will allow you to change the status, reassign the item, and add comments if desired.

action to in O S P dialog

Add any explanatory comments you wish, reassign the item if necessary, then click on the In OSP button to complete the process. The pop-up window will close, and the item details page will refresh showing the new status.

Note: If you change an Admin Action assigned to the location File back to In OSP status, the system displays a warning message, which reads:

“An Admin Action with status of In OSP may not be assigned to File. Please modify the status or the assignment.”

To complete the process, you will need to reassign the Admin Action to a value other than File.

November 2012

FEATURES

  • Automatic holds will be applied to funding actions when either training requirements or disclosure requirements have not been met
  • Ensure correct values appear for SFI on control sheet
  • New JIT functionality for FCOI
    • OSP can trigger JIT notifications in SPAERC
    • JIT notifications will be sent to
      • Any investigators who have not yet taken training
      • Any investigators who have not yet completed disclosures (important for existing eGC1s)
      • Preparers and Owners to let them know that JIT has been invoked, and that they need to make sure that everyone who should be listed on the eGC1 personnel page is actually listed there
  • JIT will trigger the status change from “Waiting for JIT” to “Review Required”  this is on the PI and Personnel page as well as in FIDS.
  • JIT notifications are not sent for RRF sponsored applications at the time FA is created.
  • Biennium field added to FA’s and PAC’s as optional to fill out.

FIXES

  • A bug was fixed to correct an Orphan session issue where when a subcontract item was opened and then the FA was opened from the subcontract page the subcontract will no longer stay open in the background. This solves one area where the user had a stale session and a 45 minute lock on the subcontract item.
  • Data clean up on some FA’s that were previously marked as duplicate that were accidentally changed to Processed. We are returning them to their duplicate status. This is to help with the EDW work.