An eGC1 for a Non-Award Agreement is how OSP receives your request to review an agreement. Approval of the eGC1 by OSP does not imply approval or acceptance of the agreement. Review more details on the NAA approval process [1] and when you need to use an eGC1.

Contents

When do I need an eGC1? [5]

Required Fields

image displays navigation within SAGE, purple circle around check for errors and a purple arrow pointing to its location

The SAGE system requires certain eGC1 fields have an entry before it will allow you to route any eGC1 to OSP. Use Check for Errors [6] on the eGC1 to find out which fields the system requires.

Other fields, while not required by the system, are required by OSP and noted in these instructions.

eGC1s with incomplete or incorrect information in the OSP required fields will be returned which may delay processing your request.

Non-Award Agreement eGC1 Instructions

Instructions for completing a non-award agreement [7] eGC1 include information on which fields are required by OSP and by SAGE.

Details Page

System required fields on the Details page include: Full Application Title, Short Title, Start and End Dates, Application Type, Project Type, Sponsored Program Activity (SPA) Type, and Sponsor fields.

PI, Personnel, & Organization Page

Enter the name of the Investigator [8], and any Senior / Key Personnel who will have the confidential discussion, handle the data or material, work on the project, etc.

Contacts & Assign Access

Enter the Administrative Contact (could be the same as the eGC1 preparer). This is the person we will contact with questions.

Abstract & RFA/RFP

OSP requires this information.

Describing the purpose and goals in detail so that OSP understands the nature of the transaction can help prevent delays in processing your request.

Activity Locations

Required by the system (all three sections). Enter the location where the activity will occur and click through the other two sections. For example: If you generated the data you are transferring in your lab at SLU, list the SLU location.

Budget & Fiscal Compliance/Cost Sharing

Tab straight through both of these sections. There is nothing required here.

Non-fiscal Compliance

All sections (Human Subjects, Animal Use, Environmental H&S, Equipment & Materials, Data & Technology) are required by SAGE. The answers here help OSP understand the terms that may need to be addressed in the agreement. In some cases additional approvals, licenses or tech transfer review might be needed before you proceed.

Confidential Disclosure Agreements/ Non-Disclosure Agreements (CDA/NDA) and the Human Subjects Section

CDAs and NDAs are most often used for preliminary discussions of a potential research project. Remember that, on the eGC1 for a CDA / NDA, these questions relate only to the information that will be disclosed in the preliminary discussion — not to the information that will be shared later for the actual project.

It is very rare for human subjects data to be disclosed in a preliminary discussion, and an unnecessary “yes” answer in this section will delay processing of your agreement.

Attached Documents

NAA Approval Process

After eGC1 routed to OSP, a reviewer is assigned who confirms that the required info is included.

Once info on eGC1 is confirmed, OSP reviewer:

NAA Status & Holds

On occasion, an NAA may be placed on HOLD for various reasons.

NAA Compliance Holds

Holds for compliance are placed based on responses to the eGC1 compliance questions.
Compliance Area eGC1 Question Why Hold Placed / Review areas More Information & Guidance
Human Subjects HS-1 OSP must be able to verify related IRB protocol approvals or exempt status information. Questions about Human Subjects Research at the UW?Contact Human Subjects Division via email: hsdinfo@uw.edu [12]
Animal Use AU-1 OSP is verifying IACUC protocol information related to the project. Contact OAW [13] for guidance on animal use in research
Equipment & Materials E-2 OSP is reviewing terms of the award to determine if further review or licensing is required. Review Equipment Fabrication [14] guidance. Contact eio@uw.edu [15] with questions

If University-owned biological materials will be provided to non-UW parties. Review Material Transfer Agreement [16] FAQs

If your project involves sharing or shipping items to or from foreign locations or with foreign nationals:

Review Export Control Measures [17]

Contact exports@uw.edu [18] with questions

Data & Technology D-1 thru D-4 OSP is reviewing to determine if further review or licensing is required. Review more information on:

Questions about export control? Email exports@uw.edu [18]

SFI/FCOI SFI/FCOI Up to date OSP is ensuring all disclosures are made by Investigators, and that an FCOI review is complete. One or more investigators on PI, Personnel & Organizations page lists SFI of “Yes” or “Unknown”

Other NAA Holds:

Hold Title / Type of Hold Description
Pending Fully Executed Agreement OSP is waiting for sponsor signature.
Other (Campus)
  • Dept. needs to submit PI confirmation, back-up documentation, or other necessary information to complete a Funding Action.
  • OSP is waiting for information from another central office.
Other (Sponsor) Revisions or additional info needed from the sponsor
PI Signature PI Signature needed