(Approved by the President by delegations of authority Executive Order No. 4 and Executive Order No. 63 )
This policy provides a framework to ensure appropriate decisions are made, documented, and approved in compliance with requirements of the state of Washington.
New technology can involve significant resources and require public accountability in making cost-effective decisions. Accordingly, every University information technology (IT) acquisition and project must comply with:
This policy applies to every IT acquisition or project conducted within any unit or by any individual throughout the University, including all campuses, colleges, schools, departments, centers, hospitals, clinics, and/or other units administered by the University and regardless of the source of funding.
The scope is to be construed broadly and includes all IT-related equipment, services, contracts, and content, including but not limited to:
Concept Plan—An early stage document outlining the general intent of the project. It identifies the business problem or opportunity to be addressed with a technology solution, the benefits to be achieved, and includes a preliminary determination of the oversight level.
Investment Plan—A formal document for justifying and obtaining approval for the project being proposed. It describes the purpose of the investment, states the business justification including benefits, and assesses risk and severity of possible impacts. It describes the acquisition process, the timeline for implementation, and lists costs, including project cost and ongoing operations cost.
Investment Plan Amendment—A revision to the original investment plan, when there is a significant increase in the project cost, or expansion of scope or schedule, which occurs after the project has been approved (for example, because of unforeseen additional expenses or an extended project duration). An increase is significant if the change escalates the project to a higher oversight level or might disqualify it from a small project exemption or other exemption.
Large Project—A project or acquisition that has an oversight level of 1 and has a project cost greater than a specific amount (initially $1 million), or has a system life cost over a specific amount (initially $2.5 million), or otherwise does not meet the definition of a small project.
Major Project—A project or acquisition that has an oversight level of 2 or 3, regardless of whether it is exempt or not from State CIO approval.
Ongoing Operations Cost—All the costs to operate and maintain the technology investment once it has been implemented. This includes expenses such as support staffing, license renewals, subsequent hardware and software purchases and services as needed to keep the system operational, lease and other recurring costs such as cloud-based expenses, and applicable taxes. Also, University employee staff time with fully-loaded dollar value must be included in these costs.
It should be noted that if the project will involve a shift from an internal "on-premise" IT system to a cloud-based system (whether Software as a Service, or Infrastructure as a Service), that the types of costs—both investment and operational—will differ in some significant ways. Additional information about the nature of those different types of costs can be found in the UW-IT Investment Procedures.
Oversight Level—An assessment of the risk and severity levels of the project determined using State CIO assessment procedures.
Project Cost—The development and implementation costs required to make an IT resource/project fully operational. Project cost includes but is not limited to: all purchases, lease, or finance costs for hardware, software, networking and telecommunications equipment, and related services; installation, training, personal and purchased services; internal University resources; and all applicable taxes. University employee staff time with its associated dollar value, including benefit load, must be included in these costs regardless of how that staff time is funded.
Project Plan—The project plan documents the baseline that will be used to measure and report project progress. It describes a management methodology that is appropriate to the scope, size, risk, cost, and duration of the specific project, and employs project management principles and methods that reflect leading IT practices.
Small Project—A project or acquisition that has an oversight level of 1, below a specific amount (initially $1 million) in project cost, has a system life cost below a certain amount (initially $2.5 million), requires no central resources or new central system integration interfaces, and has no impacts on other departments or services outside the unit undertaking the project or acquisition.
Standard IT Solutions—As defined under the authority of the CIO, a Standard IT Solution is a technology solution for a given set of capabilities where the University would like to leverage the Standard IT Solution over other solutions. These Standard IT Solutions are described in IT Standards documents.
System Life Cost—The combination of project cost and ongoing operations cost for a specific period of time (initially five years) following project completion.
With its different sources of funding and wide range of IT needs, the University has a decentralized approach to making technology investment decisions. However, there are overarching guidelines that need to be considered for the responsible planning and management of resources, regardless of the technology being acquired or implemented, or whether the technology is implemented centrally or by individual University units or departments. These considerations include but are not limited to:
The Vice President for UW-IT and CIO has delegated authority in Executive Order No. 63 to provide leadership, guidance, and oversight for all aspects of IT investments. In addition, the University's IT governance boards have oversight responsibilities for IT investments.
The University does not have statutory authority to acquire business and administrative IT equipment, software, services, or contract items of any kind regardless of the source of funds. In Chapter 43.105 RCW, the legislature has delegated the authority for approval of all IT acquisitions to the state's Chief Information Officer (State CIO), subject to certain exemptions, with the ability to delegate such authority to agencies of state government. The State CIO has delegated to the Vice President for UW-IT and CIO the authority to approve certain IT projects in accordance with state IT policy and standards.
State of Washington approval and oversight for IT is based on two considerations that are different from the acquisition of other types of goods and services:
In addition, financial or administrative system investments may require approval by the Washington State Office of Financial Management (OFM), which will be requested by the Vice President for UW-IT and CIO.
As part of planning for an IT project, it is necessary to identify all costs associated with the project, and to submit requests for approval.
Note: The office of the State CIO may from time to time make changes to the policies and requirements for IT project approvals. Any subsequent changes will be reflected as updates in the UW-IT Investment Procedures and IT Standards, and those updates will prevail over the requirements defined in this policy.
An acquisition and/or project is exempt only from state approval and oversight when that exemption is determined explicitly and documented by the Vice President for UW-IT and CIO as a project or acquisition meeting the state and University requirements for exemption. The exemptions include:
A. | Academic Exemption An Academic Exemption is available only to technology acquisitions or projects that are primarily for conducting research, or other scholarly activities, or for instructional activities. However, proposed academic applications that are enterprise-wide in nature relative to the needs and interests of other state institutions of higher education must be disclosed by the Vice President for UW-IT and CIO to the State CIO. |
||
1) | Projects and acquisitions that qualify under the above criteria are exempt from the following sections: Section 5, State of Washington Approval and Oversight; Section 10.B, Quality Assurance; and except for Level 3, Section 10.C, Status Reporting. They must comply with all other provisions of the policy, except as noted in Items 2) and 3) below. |
||
2) | In addition, if the project or acquisition is Level 1, then it is also exempt from Section 9, State Reporting Requirements and Investment Plan. |
||
3) | Furthermore, if the project or acquisition is Level 1 and under $1 million in project cost and impacts only a single department, then it is also exempt from the following sections: Section 8.A, Vice President for UW-IT and CIO Approval of Investment Plan; and Section 10.A, Concept Plan and Project Plan. |
||
4) | Any such project or acquisition that is categorized as a major project (has an oversight Level 2 or 3), if longer than 12 months in duration, is subject to ongoing status reporting. |
||
Note: The following acquisitions and IT system projects are examples that do not qualify for an Academic Exemption: administrative, business, financial, billing, payroll, personnel, budget, student record, student billing, inventory, scheduling, document imaging or management, project management, facilities management, enterprise resource planning (ERP), purchasing, storehouse, web portal, contract and grant management, customer relationship management, point of sale. Given the varied uses of technology at the University, any department head who believes an IT acquisition that has been unfairly denied for an Academic Exemption may write to the Vice President for UW-IT and CIO to request a review of the initial decision. |
|||
B. | Health Care Related Exemption A "medical, clinical, or health care application including business and administrative applications" is exempt from State CIO approval and reporting but is subject to institutional reviews, approvals, and oversight. Any such project must be conducted in accordance with a memorandum of understanding (MOU) between the Vice President for UW-IT and CIO and UW Medicine, or any University health care-related project that is outside the scope of the UW Medicine MOU will be treated as outlined for other projects in terms of University approval and institutional oversight. |
An acquisition and/or project may be exempt from University approval and oversight (small project exemption) when that acquisition and/or project is under a certain cost (initially $1 million in total project cost and under $2.5 million in system life cost), is a Level 1 project, and the impact is within a single department. These projects should still align with and leverage the Standard IT Solutions where feasible.
A small project exemption requires a determination of the oversight level and a determination of total system life cost but does not require prior approval or oversight from the Vice President for UW-IT and CIO. However, the University department undertaking that acquisition or project must be able to demonstrate qualification for the oversight level and the system life cost to support the exemption upon request.
A project or acquisition does not qualify for this small project exemption if any of the following is true:
While University leaders are responsible for key strategic technology issues, directions, policies, plans, and priorities within their areas of responsibility, all University IT projects and acquisitions that meet the criteria of this policy are subject to provisions of this policy, including the review and approvals stipulated below.
All official communications with the State CIO must be approved in advance by the Vice President for UW-IT and CIO. Official communications include but are not limited to concept plan, new or amended project investment plans and supporting information, and project status reports. UW-IT can provide guidance in preparing materials for submission to the state. Procedures and templates are available in the UW-IT Investment Procedures.
A. | State Requirements for Non-Exempt Projects and Acquisitions The state requirements for non-exempt projects and acquisitions include:
|
|
B. | University Requirements for Projects and Acquisitions Exempt from State Oversight For projects and acquisitions that are exempt from state oversight, the University requirements include:
|
|
C. | Investment Plan Amendments Projects may need to make adjustments in scope, cost, schedule, and other factors during execution of a project or at any other time after submitting the original investment plan. Project oversight / steering committees and sponsors must determine whether the project's prior approved status as exempt or non-exempt and its oversight level remain unchanged, and if either are changed, whether another review and approval by the Vice President for UW-IT and CIO is necessary. |
There are several established practices in the successful management of any IT project, including development of a concept plan, feasibility and readiness studies, development of a project plan, ongoing QA assessments, and project status reporting. For certain types of projects the following practices are required:
University Procurement Services will execute the acquisition or contract commitment once the appropriate action is taken by the Board of Regents in accordance with current Board of Regents Governance Standing Orders, and upon being informed that all the approvals and requirements of this policy have been fulfilled.
Authoritative and updated information about current requirements and procedures is available at:
July 14, 2005; May 11, 2016; December 21, 2021.