Problem with PI if incorrect budget linked to eGC1

If the PI is changed on an eGC1 as a result of accidentally connecting an incorrect budget to an eGC1, the original PI is not reverted back when the budget is disconnected. Follow the steps below to put the correct PI in place.

Workaround

Steps to display the current PI in SAGE:

  1. Create a new standard eGC1
  2. Add a Full Title (Details page)
  3. Add the correct PI (PI & Personnel page)
  4. Link to the Budget for the Budget/eGC1 group that needs correction (Budget page)
  5. Disconnect the Budget
  6. Return to My eGC1s page to verify who is now listed as PI
  7. Optionally, delete the eGC1 just created