GIM 9
Advance Budget Number Assignments (Advance Notices)
UNIVERSITY OF WASHINGTON
Office of Research
Office of Sponsored Programs
GRANTS INFORMATION MEMORANDUM 9
May 16, 2001
SUBJECT: Advance Budget Number Assignments (Advance Notices)
This memorandum is to outline the procedure for the expenditure or
commitment of funds against a grant, contract or other agreement prior to
the receipt of an executed award document.
I. GENERAL POLICY
The Principal Investigator of a contract, grant or other agreement may
request authorization to spend a limited amount of money during a
specified period on an Advance Notice prior to the receipt of an executed
award from the funding agency. This need often arises when an award has
not been received in Office of Sponsored Programs (OSP) by the effective
date of the award.
An established procedure is already in place for automatic assignment of
non-competing (continuation) budget numbers for National Institutes of
Health, Department of Energy and Department of Education grants provided
an official University proposal is on file.
II. PROCEDURE
The Principal Investigator is advised by the sponsor that an award
is forthcoming. The PI completes the Memo to Request an Advance Notice
form (See Attachment A), providing all information required for budget
setup as indicated. The form is signed by the PI and the Chair or Dean of
the Department and then sent to Grant and Contract Accounting (GCA). The
request should:
Explain the need for the Advance Notice, and the proposed advance
period. An advance budget can be requested for up to the maximum of six
(6) months.
A subsequent increment of the advance budget to a maximum of three
(3) months can be requested by memo, or email, to GCA at the end of the
first period. The request must guarantee any additional advance funding.
The second request must be signed by the PI and Dean/Chair (for email,
both must concur by email).
GCA establishes a budget number with a short title denoted by
*ADVANCE* and informs the Principal Investigator or Administrator as noted
on Attachment A (UW contact name/email).
Advance Notice requests will not be processed for a proposal with
Significant Financial Conflict of Interest (see GIM 10) until the approval
is obtained.
Requests to establish advance budgets for Industry Sponsored and
Clinical Trial agreements should be sent to Office of Sponsored Programs
(OSP) for review and processing (See Attachment B).
The PI or Department Administrator will monitor advance budget
expenditures and notify GCA within (10) working days prior to advance
budget expiration to request a second advance if an award has not been
received by that time. An Advance budget will not exceed 12 months.
The PI and Department Chair will be responsible for any pre-award costs
that are not allowed by Sponsor as well as any amounts authorized by the
advance but not funded by the Sponsor.
When OSP receives an award from the sponsor, OSP staff will review
the Online Financial Accounting System to verify that an advance budget
has been authorized, a final NEA will be completed and sent to GCA with
notification that an Advance Notice was previously set up for the subject
account.
Carol Zuiches
Executive Director, Office of Sponsored Programs
Assistant Vice Provost for Research
Sue Camber, Assistant Controller
Research Accounting and Analysis
Attachment A: Memo to Request an Advance
Notice (Federal and Non-Industry Sponsors)
Attachment B: Memo to Request
an Advance Notice (Industry Sponsor & Clinical Trial Agreements)
Attachment C: Advance Notice Instruction
Sheet |