How to Fill Out a Purchase Req. for a Subcontract in PAS
The instructions below are specific to requesting a purchase requisition for an outgoing subcontract.
Step 1

- Enter 1: Requisition Entry.
Step 2

- Enter the primary budget number to be used to fund the subcontractor.
Note: More than one (1) budget cannot be used. Prime sponsor funding cannot be co-mingled with other funding.
Step 3

- Confirm auto-populated fields.
- Always select No for attachments.
Note: The service begin and end dates must align with the prime sponsor budget period and available funding.
Step 4

- Record the Purchase Requisition (PR) number when you get to this screen so that you are able to return to PAS and find this requisition in the future.
Step 5

- OSP outgoing subcontract staff cannot complete the subcontract without an official, signed work scope and budget approved by the UW PI or designee.
Step 6

- Look up the vendor's name in PAS, using Vendor Search (Enter 7 in Action box).
- Select the appropriate vendor name.
Note: The vendor name is the same as the Subcontractor.
Step 7

- Enter the dollar amount in the Unit-Price box (do not include pennies).
- Always enter 03-62 in the Object code box.
If you enter another object code, the requisition will not be processed by OSP Staff.
Note: You can only fund what you have available and the authority to do under the prime award.
Step 8

- Confirm the total amount of subcontract, and that no Washington taxes will be charged.
- If modifications need to be made, enter the number 4
Step 9

- Always enter 2 in the choice field.
Step 10

- Type one of the two options. If the second option is selected, provide a scientific or technical description of the collaboration between the two PIs.
Step 11

- This screen is a summary of all the information previously entered.
- Enter 6 (Encumber) to send the PR to OSP to begin the preparation of the subcontract document.
For more information visit the PAS Requisition Entry page.

| 